Problem
Dependencies that circle back on themselves leave no valid run order, and that case has to raise rather than hang or return a partial result. Otherwise tasks maps each task name to its deps and an op such as "add 3" or "mul 2", applied to the combined output of those deps once they have all run; return every task's output keyed by name, or an empty result when tasks is None or empty.
Nothing runs until what it needs has run.
Example 1
Input:
tasks = {"load":{"op":"add 0","deps":["clean","enrich"]},"clean":{"op":"add 1","deps":["extract"]},"enrich":{"op":"mul 2","deps":["extract"]},"extract":{"op":"add 10","deps":[]}}Output:
{"load":31,"clean":11,"enrich":20,"extract":10}Example 2
Input:
tasks = {"score":{"op":"mul 3","deps":["ingest"]},"ingest":{"op":"add 2","deps":[]},"publish":{"op":"add 5","deps":["score"]}}Output:
{"score":6,"ingest":2,"publish":11}Worked solution and explanation
What this problem really is
Take off the orchestration costume and this is dependency-ordered graph execution. A task needs its prerequisites' outputs in hand before it can run, and those outputs have to flow forward into it. Everyone can parse 'mul 2'. What separates candidates is noticing that dict order is not run order: in the first example load is listed before extract, so a single pass reads outputs['clean'] before it exists and dies with a KeyError. And when the graph circles back on itself, a naive retry-until-done version spins forever waiting on tasks that can never become ready.
Break down the requirements
Step 1: Build the waiting counts and the reverse edges
waiting_on holds each task's count of unfinished dependencies; dependents inverts the edges so that finishing a task tells you whom to notify. Building the reverse map up front is what keeps each edge to one visit.
Step 2: Seed the queue with the roots
Every task with zero dependencies goes into a deque. These are the roots; their combined input is 0, which is why 'add 10' on extract yields 10 and a root 'mul' would yield 0.
Step 3: Run a ready task, then release its dependents
Split op into a verb and an amount, convert the amount with int, sum the dependencies' stored outputs, and apply the verb. Then decrement each dependent and queue any that reach zero. load in the first example only becomes ready after both clean (11) and enrich (20) finish, giving 31.
Step 4: Count what ran to catch the cycle
When the queue drains, either every task has an output or some tasks were never released. The second case can only mean a cycle, so compare len(outputs) to len(tasks) and raise.
The solution
import operator
from collections import deque
OPERATIONS = {'add': operator.add, 'mul': operator.mul}
def execute_dag(tasks):
if not tasks:
return {}
waiting_on = {name: len(spec['deps']) for name, spec in tasks.items()}
dependents = {name: [] for name in tasks}
for name, spec in tasks.items():
for dep in spec['deps']:
dependents[dep].append(name)
ready = deque(name for name, count in waiting_on.items() if count == 0)
outputs = {}
while ready:
name = ready.popleft()
spec = tasks[name]
verb, amount_text = spec['op'].split()
try:
apply_op = OPERATIONS[verb]
except KeyError:
raise ValueError("task '" + name + "' has unknown op '" + verb + "'")
combined = 0
for dep in spec['deps']:
combined += outputs[dep]
outputs[name] = apply_op(combined, int(amount_text))
for child in dependents[name]:
waiting_on[child] -= 1
if waiting_on[child] == 0:
ready.append(child)
if len(outputs) != len(tasks):
raise ValueError('cycle detected: some tasks can never run')
return outputsCommon follow-up questions
- A task fails halfway through the run. What should happen to the tasks downstream of it? (Tests wrapping each task's execution and deciding whether downstream tasks are skipped or the run aborts.)
- How would you run independent tasks concurrently instead of one at a time? (Tests dispatching every zero-count task in a wave to a worker pool.)
- How would you resume a partially completed run without redoing finished tasks? (Tests persisting `outputs` and re-seeding the counts from what already finished.)
- How would you tell the user which tasks form the cycle? (Tests reporting the actual cycle path rather than just the leftover set.)